           006 ACCOMMODATIONS/FACILITIES, TRASH AND SEWAGE SERVICES

    a.  REFUSE  COLLECTION:  Provide  90  each,  5  C.M. dumpsters  for  tent
    city and remainder of base.  Dumpsters shall be placed on site as
    shown in attached site plan.  Dumpsters  shall  be  emptied  on  a  seven
    day per  week  schedule  emptying  45  dumpsters  per  day.  Contractor
    shall haul all  waste  to  an  off  base  disposal  point.  Contractor  shall
    begin delivery of  5 C.M. dumpsters  on  26  Nov  90  and  continue  until
    all 90 are in place.  Contractor  shall  begin  pick  up  schedule  on  27
    Nov 90 of approximately 20  dumpsters  and  continue  pick  up  of  these  20
    dumpsters every other day until 10  Dec  90.  Full  service  pick  up  of
    45 dumpsters every other day shall begin on 11 Dec 90.

    b.  PURCHASE  AND  SERVICE  OF  PORTABLE  RESTROOMS:   Purchase
    75-Poly-Plus  or  equivalent  portable  restrooms  with  holding  capacity
    of approximately 40 gallons.  Portable restrooms are to be delivered
    to base and  placed  in  locations  shown  on  attached  map.  Portable
    restrooms shall be  delivered  starting  with  20  -  portable  restrooms  on
    26 Nov 90, with the remainder  of  the  portable  restrooms  (55)  to  be
    delivered by 10 Dec 90.   Daily cleaning and pumping service of these
    75  portable  restrooms  shall  include  equipment,  vehicles,  manpower  and
    chemicals  necessary  to  maintain  and  service  these  portable  restrooms.
    Service shall start on initial 20 portable restrooms on 26 Nov 90
    with full service on all  75  portable  restrooms  beginning  on  12  Dec
    90.

    Suggested source for Portable Restrooms and Service:
    International Electromechanics Center (IEC)
    P.O. Box 7518
    Riyadh 11472 Saudi Arabia
    Tele 4542000
    POC  P.K.  Krishnan/Hashim  Mahdaly

		                                            ESTIMATED       ESTIMATED
    COST:          	      QUANTITY     UNIT       UNIT PRICE       TOTAL   COST
    Portable Restrooms    75       	      ea.  	 855       	 64,125
    Service                   	 6           Months        13,875      		 83,250
                                                                                                 ----------------
                                                       			 Total   147,375

    c.  PUMP  OUT  SEWAGE  HOLDING  TANKS:  Provide  sewage  pumping  service
    for 9-10,000 liter sewage holding  tanks  twice  on  each  tank  per  day
    seven days per week.  Tanks  shall  be  pumped  from  locations  shown  on
    attached  map.  Sewage  shall  be  pumped  from  holding  tanks  and  disposed
    of at an off-base location.  Service shall begin on 1 Dec 90.

    d. PUMP GREASE  TRAPS:  Pump  out  2  each  grease  traps  located  behind
    each Dining Hall.  Grease  traps  are  to  be  cleaned  and  pumped  out
    every other day at least  three  days  per  week.  Each  grease  trap  may
    hold up to 1,000  gallons.  Contractor  shall  dispose  of  waste  at  an
    off-site location.  Service shall begin on 10 Dec 90.

    e. USED  OIL  AND  SPILLED  FUEL:  Contractor  shall  remove  used  waste
    oil and spilled diluted fuel, and shall provide for disposal of
    oily/greasy rags once each week.  Contractor shall provide 500 clean