FACILITY TO STORE REFUELER MAINTENANCE EQUIPMENT.

(2)	PROPOSED SOLUTION:  A PORTABLE HANGAR JUST ARRIVED TO COVER
THIS REQUIREMENT.  THANKS!

PART III.   (U)   COMBAT SUPPORT.

1.	THE COMBAT SUPPORT ELEMENT IS FULLY MANNED AND PROVIDING ALL
REQUIRED SUPPORT.

A.	PROBLEM:  THE CIVIL ENGINEER LACKS THE 5KV, 1/0 ALUMINUM
CABLE REQUIRED TO INSTALL THE 4.16KV TRANSFORMERS.

(1)	DISCUSSION:  ALL TRANSFORMER PARTS HAVE BEEN FOUND.  THE
5KV, OT CABLE IS BEING SOURCED AT MYRTLE BEACH AFB SUPPLY.

(2)	PROPOSED SOLUTION:  HQ CENTAF/DE COORDINATE SHIPMENT ONCE



PAGE 06 RHIEFBA0356
PURCHASED.

(3)	REQUESTED SUPPORT:  DIRECT THE SHIPMENT OF THE 50,000 FEET
OF CABLE FROM THE CONUS TO THIS SITE.

	PROBLEM:  TWO SHOWER/SHAVE UNITS, ONE EXPANDABLE SHELTER
TWO SDC ARE REQUIRED TO SUPPORT 1ST SOW AND 31 ATH.

1)	DISCUSSION:  ONE SHOWER/SHAVE UNIT REQUIRED TO BRING THE 1
SOW UP TO THAT REQUIRED PER PERSON.  THE SECOND SHOWER/SHAVE REQUIRED
TO SUPPORT THE 31 ATH -- IT WILL BE 31 ATH'S ONLY SHOWER/SHAVE
FACILITIES FOR PATIENTS.  EXPANDABLE SHELTER REQUIRED FOR CIVIL
ENGINEERING SHOP SPACE AT 1 SOW CAMP.  SDC'S REQUIRED TO POWER
SHOWER/SHAVE UNITS AND SHELTER.

2)	PROPOSED SOLUTION:  HQ CENTAF/DE SOURCE ASSETS.

3)	REQUESTED SUPPORT:  DIRECT THE SHIPMENT OF 2 SDCS, 2
SHOWER/SHAVE UNITS, AND ONE EXPANDABLE SHELTER TO THIS SITE.