                      CRIITICAL EQUIPMENT STATUS - RAPID RUNWAY REPAIR
         
         
                      	PRIMARY   THREAT
LOCATION    	AIRCRAFT  PRIORITY  	STATUS  	LIMFACS/COMMENTS
         
AL AYN    	C-l30
AL DHAFRA   F-16
AL MINHAD  	F-16
BATEEN      	C-130
CAIRO       	KC-l35
DHAHRAN 	F-15           	4      		UNSAT 	SEE NOTE 1          
     [(b)(1)SEC3.4(b)(5)]
DOHA              F-16		5      		UNSAT 	SEE NOTE 1        
JEDDAH KC-135
     [(b)(1)SEC3.4(b)(5)]
K. FAHD  	A-10        	1      		UNSAT 	SEE NOTE 2
KHALID 	KC-135
MASIRAH 	C-l30
RIYADH 	E-3A
SEEB 		KC-135
SHAIKH ISA 	F-4G       	2      		UNSAT 	SEE NOTE 8
SHARJAH 	C-l30
TABUK 	F-15            	3      		UNSAT 	SEE NOTE 1
TAIF   		F-111
THUMRAIT 	F-15
       
NOTE 1:  HEAVY EQUIPMENT SOURCED.  LGT IS WORKING SHORTFALLS WITH HQ
             TAC/LGT.  AFESC IS WORKING FIBERGLASS MAT TO FILL SHORTFALL OF
             AM-2 MAT SYSTEM. FIRST 2 KITS OF 4 PATCHES EXPECTED TO BE READY
             FOR SHIPMENT ON 24 OCT 90.  NO AM-2 AVAILABLE TO POSITION MATS AT
             THESE LOCATIONS.
                
NOTE 2:  AM-2 MAT SYSTEM ARRIVED 6 OCT 90.  KITS MISSING PARTS.  SITE
            IS PEFORMING A DETAILED INVENTORY.  NINE INCOMPLETE PATCHES ON
            SITE BUT HEAVY EQUIPMENT STILL IN TRANSIT.
             
NOTE 3:  375 BUNDLES AM-2 MAT ON SITE BEING USED TO DISPERSE AIRCRAFT.
         	TOW TUBES, RAMPS, ETC., FOR NINE PATCHES ARRIVED 5 OCT 90.
             HEAVY EQUIPMENT SOURCED BUT DUMP TRUCKS CURRENTLY BEING 	USED 
AT AL DHAFRA TO BUILD MUNITIONS BERMS.
             
             
             
             							AS OF 20 OCT 90