          6.  ALDH 910100 (AF 744) Expand Apron, Al Dhafra, UA-
              
          - Scope:  Expand aircraft parking apron to support additional cargo
            and tanker aircraft, 191,100 SF.  Excavate, backfill, and overlay
            taxiway to adjust drainage.

         Funded Cost: $1,202.2K Unfunded Cost:   $282.6K Total Cost: $l.484.6K
         Funding Source: GOJ
         ESD: 28 Jan 91                       ECD: 15 Mar 91
         Status: CENTCOM approved 20 Jan 91.
         Site POC: [(b)(2)]

         7.  ALDH 91-0101 (AF 745), Install Commercial Power, Al Dhafra, UAE

         - Scope:  Install commercial power to avionics facility.
            
         Labor:  RED HORSE
         Funding Source:  GOJ                            Total Cost:  $58.2K
         ESD:  TBD                                       ECD:  TBD
         Status:  RH to evaluate and prepare new 1391 for troop labor.  CENTCOM
         awaiting quotes from Al Dhafra.
         Site POC:     [(b)(2)]
         
     8.  ALDH 910102/3/4 (AF 746), Commercial Power at Communication Sites,
         Al Dhafra, UAE
         
          - Scope:  Install commercial power to three separate communications
            sites.
            
         Labor:  RED HORSE
         Funding Source:  GOJ                            Total Cost:  $560.3K
         ESD:  TBD                                            ECD:  TBD
         Status:  RH to evaluate and prepare new 1391 for troop labor (Lt Sambora).
         CENTCOM awaiting quotes from Al Dhafra.
         Site POC:      [(b)(2)]
         
         9.  ALKH 91-0001 (AF 021), Construct Munitions Storage Area, Al Kharj AB,
         S.A.
         
          -Scope:  Construct 12 ea 50x100 and 5 ea 50x50 K-Spans, plus two 50 x
            100 K-Spans in 4 TFW MSA, 14 miles of munitions storage roads
            (clay).
            - 7,410 meter chain link fence by contract.
            - Pave entrance road (1.6 mi)
            
         Funded Cost: $1,664.9K Unfunded Cost: $306.9K       Total Cost: $1,971.8K
         Funding Source: Saudi
         ASD: 15 Oct 90 			ECD:  31 Jan 91
         Status:  Clay roads complete.  Entrance road paving complete.  Fence
                  contract 100% complete.  6 - 50 X 100 and 4 - 50 X 50 K-Spans
                  complete on hold, awaiting additional steel.
         
         10.  ALKH 91-OOlA  (AF 731), Pave Munitions Storage Area Roads, Al Kharj
         AB, S.A.
         
            - Scope:  Pave 14 miles of clay roads with asphalt in MSA.
            
         Funded Cost: $962.OK   Unfunded Cost: TBD     Total Cost: TBD
         Funding Source:  Saudi
         ASD:  12 Dec 90                          ECD:  31 Jan 91
         Status:  50%  Pavina in proqress.
         