		CRITICAL EQUIPMENT STATUS- RAPID RUNWAY REPAIR 
 
 
			PRIMARY	THREAT 
LOCATION		AIRCRAFT	PRIORITY	STATUS		LIMFACS/COMMENTS 
 
AL AYN			C-130 
AL DHAFRA		F-16 
AL KHARJ		 
AL MINHAD		F-16 
BATEEN			C-130 
CAIRO			KC-135 
DHAHRAN 		F-15		4		UNSAT		SEE NOTE 1 
DOHA			F-16		3 		UNSAT		SEE NOTE 2 
JEDDAH			KC-135		 
			[(b)(1) sec 3.4 (b)(5)] 
K. FAHD			A-10		1		UNSAT		SEE NOTE 3 
KHALID 		KC-135	 
MASIRAH		C-130 
RIYADH			E-3A	 
SEEB			KC-135	 
SHAIKH			F-4G		2		UNSAT		SEE NOTE 4 
SHARJAH		C-130 
TABUK			F-15		5		UNSAT		SEE NOTE  1 
TAIF			F-111 
THUMRAIT		F-15 
 
NOTE  1: HEAVY EQUIPMENT SOURCED.  LGT IS WORKING SHORTFALLS WITH HQ 
	TAC/LGT.  AFESC IS WORKING FIBERGLASS MAT TO FILL SHORTFALL OF 
	AM-2 MAT SYSTEM.  FOUR PATCHES (FIBERGLASS) MAT SHIPPED FROM 
	CONUS ON 24 OCT 90 BUT HAS NOT YET ARRIVED AT SITE.  
 
NOTE 2: LG WORKING SHORTFALL OF VEHICLE FROM CONUS.  NO AM-2 MAT SYSTEM 
	AVAILABLE FOR THIS SITE.   SITE SCHEDULED FOR NEXT AVAILABLE FIBER- 
	GLASS MAT SET CURRENTLY BEING PRODUCED.  
 
NOTE 3: AM-2 MAT SYSTEM ARRIVED 6 OCT 90.  KITS MISSING PARTS.  SITE 
	PERFORMED A DETAILED INVENTORY AND LISTED SHORTFALLS IN THEIR 
	SITREP.  NINE INCOMPLETE PATCHES ON  SITE BUT HEAVY EQUIPMENT STILL 
	IN TRANSIT.  THERE IS STILL A SERIOUS SHORTFALL OF HEAVY EQUIPMENT 
	TO PERFORM RRR. 
 
NOTE 4: 375 BUNDLES AM-2 MAT ON SITE BEING USED TO DISPENSE AIRCRAFT. 
	TOW TUBES,  RAMPS,  ETC,.  FOR NINE PATCHES ARRIVED 5 OCT 90. 
	HEAVY EQUIPMENT SOURCED BUT DUMP TRUCKS CURRENTLY BEING USED AT  
	AL DHAFRA TO BUILD MUNITIONS BERMS.  PATCHES KITS INVENTORIED AND 
	FOUND TO BE COMPLETE.  
						AS OF 10 NOV 90  
						OPR:      [(b)(2)] 
 
 
    		 
			 				 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 