USCENTAF/DE
CRITICAL ISSUE
SUBJECT: BEDDOWN STATUS OF AL KHARJ AB, 5,A.
AIRLIFT: Aircraft continue to arrive with cargo on a daily ~asis.
AIRFIELD: Airfield pavements in operational condition including
airfield lighting, Three runway sweepers on site. PAPI system
operational and has been flight checked. Portable TACAN is
operatiopal. Portable tower is operational. Working now to bring up
ASR and PXR.
ARRESTING BARRIER5: The runway has two BAK-9, two BAK-14 and two net
barriers which have not been certified, One MAAS installed on runway,
2000 feet from threshold, north end. A second MAAS installed but
needs parts. Parts sourced from 7002nd CES, Ramstein and should
arrive 24 Dec 90. A third MAAS is on-hand and will be installed on
taxiway for an alternate runway. Working with HN engineers to
activate and certify the BAK-14 barriers.
FIRE PROTECTION: Satisfactory. Five P-19's, two P-13's, one P-20 and
one P-10 on site. Three P-18's and one P-19 sourced. All 58 fire
fighters on site.
WATER STORAGE: The local host nation storage, treatment and
distribution system cannot be charged as there is no pumping station
constructed. Twenty-six storage bladders (20,000 gallon) are
required. All bladders to be installed and filled as soon as
available. Twelve 20,000 gallon bladders on-hand. Bladders are
dispersed now at latrines/showers and dining tents. A bladder farm
including ROWPU's (2 each) will be set-up as more bladders arrive.
FUEL STORAGE: There is no nation fuel storage available. Ten sets of
berms are complete now and others are under construction. Forty
50,000 Gal bladders are now capable of being filled. An additional 8
bladders for MAC operations will be ready for filling on 27 Dec 90.
POWER: No commercial power is available. 14 solar turbine generators
are on-hand (750 XW) and being used for high voltage power. Power
plant for cantonment area is up and running. flightline back-up power
plant should ready for use by 27 Dec 90. Presently running high
voltage cable from cantonment area power plant to flightline area.
CANTONMENT AREA: RED HORSE, Prime BEEF, and a Saudi contractor are
working 24-hours a day in shifts. Site prep and graded clay roads are
complete. Asphalt pad for hospital is complete. Some tac coat has
been applied to roads and asphalt work will begin NLT 24 DEC 90.
385 billeting tents and 90 admin tents are now erected.
SERVICES: One double 9-1 operational serving 2 hot meals and
soup/sandwich/salad for lunch. B-rations, MRE's for 30 day supply
on-hand. first meal served out of double 9-1 on 16 Dec 90, second
double 9-1 to be serving by 27 Dec 90. Tactical Field Exchange (TFE)
scheduled to be operational NLT 24 Dec 90. Barber concessionaire
operating in the cantonment area.