USCENTAF/DE 
CRITICAL EQUIPMENT STATUS - RAPID RUNWAY REPAIR
 
		PRIMARY 	THREAT 
LOCATION 	AIRCRAFT 	PRIORITY 	STATUS 	LIMFACS/COMMENTS 
 
AL AYN	C-130 
AL DHAFRA 	F-16 
AL KHARJ 
AL MINHAD 	F-16 
BATEEN	C-130 
CAIRO		KC-135 
DHAHRAN	F-15		4		UNSAT 		SEE NOTE 1 
DOHA		F-16		3		UNSAT 		SEE NOTE 2 
JEDDAH	KC-135 
KHAMIS	[(b)(l)sEC3.4 (b)(5)] 
K. FAHD	A-10		1		UNSAT 		SEE NOTE 3 
KHALID	KC-135 
MASIRAH	C-130 
RIYADH	E-3A 
SEEB		KC-135 
SHAIKH ISA 	F-4G		2		UNSAT		 SEE NOTE 4 
SHARJAH 	C-130 
TABUK 	F-15		5		UNSAT 		SEE NOTE 1 
TAIF		 F-111 
THUMRAIT	 F-15 
 
NOTE 1: HEAVY EQUIPMENT SOURCED. LGT IS WORKING SHORTFALLS WITH HQ 
TAC/LGT. AFESC IS WORKING FIBERGLASS MAT TO FILL SHORTFALL OF 
AM-2 MAT SYSTEM. FOUR PATCHES (FIBERGLASS) MAT KIT EXPECTED TO 
ARRIVE ANY DAY. 
 
NOTE 2: LG WORKING SHORTFALL OF VEHICLES FROM CONUS. NO AM-2 MAT SYSTEM 
AVAILABLE FOR THIS SITE. SITE SCHEDULED FOR NEXT AVAILABLE FIBER- 
GLASS MAT SET CURRENTLY BEING PRODUCED. 
 
NOTE 3: AM-2 MAT SYSTEM ARRIVED 6 OCT 90. KITS MISSING PARTS. SITE 
PERFORMED A DETAILED INVENTORY AND LISTED SHORTFALLS IN THEIR 
SITREP. NINE INCOMPLETE PATCHES ON SITE BUT HEAVY EQUIPMENT STILL 
IN TRANSIT. 
 
NOTE 4: 375 BUNDLES AM-2 MAT ON SITE BEING USED TO DISPERSE AIRCRAFT. 
TOW TUBES, RAMPS, ETC., FOR NINE PATCHES ARRIVED 5 OCT 90. 
HEAVY EQUIPMENT SOURCED BUT DUMP TRUCKS CURRENTLY BEING USED AT 
AL DHAFRA TO BUILD MUNITIONS BERMS.