			RFD HORSE Construction Project 
 
1. ALKH 91-0001, Construct Munitions Storage Area, Al Kharj AB, S.A. 
 
	-Scope: Construct 12 ea 50x100 and 5 ea 50x50 K-Spans, build 14 
	 miles of munitions storage roads (clay), and pave 1.6 miles of 
	 access road. 
	- 7,410 meter chain link fence by contract.  
 
Funded Cost: $1,664.9 			Unfunded Cost: $306.9K 
ECD: Buildings on hold for steel 
     Clay Roads 15 Dec 91 50% complete; Asphalt Roads: Contract Awarded; 
     Fence contract 5% complete 
Status: 5 - 50 x 100 And 4 - 50 X 50 K-Spans up. 
 
2. ALKH 91-0004, Beddown TFW, Al Kharj AB, S.A. 
 
	- Scope: Beddown 3800 man tent city and 114 aircraft. 
 
Cost: Funded $34.4 		Unfunded Cost: N/A 
ECD: 15 Jan 91 (Cantonment Area) 
Status: 40% 
 
3. ALKH 91-0007, Construct TFW Maint K-Spans (4), Al Kharj AB S.A. 
 
	- Scope: 2 - 50'x 80' K-Spans with end walls, lights, Conc, floors. 
	2 - 50'x 100' K-Spans, remainder of Scope TBD. 
 
Funded Cost: Unk 			Unfunded Cost: Unk 
ECD: 					Total Cost: Unk 
Status: Two 50'x 80' erected. Awaiting Steel for 2 - 50'x 100' K-Spans. 
 
4. SHAI 91-0005, Supervise Revetment Erection, Shaikh Isa AB, Bahrain 
 
	- Scope: Supervise erection of 19 B-1 revetment kits. (Does not 
	include requirements for Plus-up). 
 
Funded Cost: $34.4K 			Unfunded Cost: $154.2 
ECD: 15 Dec 90 
Status: 95% (Turned over to BCE) 
 
5. KFIA 91-0008, Supervise Revetment Erection, King Fahd IAP, S.A. 
 
	- Scope: Erect approximately 140 B-1 revetment kits for TFW. 
		 Will supervise/train for 30 days the turn over to BCE. 
 
Funded Cost: $68K 				Unfunded Cost: $304K 
ECD: Jun 91 (ABO assessing need dates vs requirements at Dhahran) 
Status: 15%, Working to accellerate construction to move ECD to Jan 91.