RFD HORSE Construction Project
1. ALKH 91-0001, Construct Munitions Storage Area, Al Kharj AB, S.A.
-Scope: Construct 12 ea 50x100 and 5 ea 50x50 K-Spans, build 14
miles of munitions storage roads (clay), and pave 1.6 miles of
access road.
- 7,410 meter chain link fence by contract.
Funded Cost: $1,664.9 Unfunded Cost: $306.9K
ECD: Buildings on hold for steel
Clay Roads 15 Dec 91 50% complete; Asphalt Roads: Contract Awarded;
Fence contract 5% complete
Status: 5 - 50 x 100 And 4 - 50 X 50 K-Spans up.
2. ALKH 91-0004, Beddown TFW, Al Kharj AB, S.A.
- Scope: Beddown 3800 man tent city and 114 aircraft.
Cost: Funded $34.4 Unfunded Cost: N/A
ECD: 15 Jan 91 (Cantonment Area)
Status: 40%
3. ALKH 91-0007, Construct TFW Maint K-Spans (4), Al Kharj AB S.A.
- Scope: 2 - 50'x 80' K-Spans with end walls, lights, Conc, floors.
2 - 50'x 100' K-Spans, remainder of Scope TBD.
Funded Cost: Unk Unfunded Cost: Unk
ECD: Total Cost: Unk
Status: Two 50'x 80' erected. Awaiting Steel for 2 - 50'x 100' K-Spans.
4. SHAI 91-0005, Supervise Revetment Erection, Shaikh Isa AB, Bahrain
- Scope: Supervise erection of 19 B-1 revetment kits. (Does not
include requirements for Plus-up).
Funded Cost: $34.4K Unfunded Cost: $154.2
ECD: 15 Dec 90
Status: 95% (Turned over to BCE)
5. KFIA 91-0008, Supervise Revetment Erection, King Fahd IAP, S.A.
- Scope: Erect approximately 140 B-1 revetment kits for TFW.
Will supervise/train for 30 days the turn over to BCE.
Funded Cost: $68K Unfunded Cost: $304K
ECD: Jun 91 (ABO assessing need dates vs requirements at Dhahran)
Status: 15%, Working to accellerate construction to move ECD to Jan 91.