10A. KKMC 91-000lA, Beddown Construction, King Khalid Military City, S.A. 
 
	- Scope: Construct 2 asphalt pads for dust control (24'x 3600'x 2 " 
	and 12'x 3600'x 2 "). 
 
Funded Cost: $65.8K 	Unfunded Cost: Unk 	Total Cost: Unk 
ESD: Unk 		ECD: Unk 
Status: To CENTCOM   Dec 90 for Saudi contract accomplishment. 
 
11. KKMC 91-0002 Construct A-10 Rearm and Maint Area, King Khalid 
Military 
 
	-Scope: Construct two asphalt pads 100' x 1000' for A-10 Rearm area 
	   and hard broke maintenance area, parallel to existing taxiway. 
	   Construct by contract. 
 
Funded Cost: 98.7K 	Unfunded Cost: 10K 	Total Cost: $108.7K 
ESD: Dec 90 	ECD: Jan 91 
Status: To CENTCOM 13 Dec for Saudi Funding & Contract. 
 
12. KKMC 91-0003, Supervise Revetment Erection, King Khalid Military 
City, S.A. 
 
	- Scope: Erect and fill 1 ea, B-1 revetment kit. RED HORSE to 
	  supervise and train user. 
 
Funded Cost: 48.3K 			Unfunded Cost: 30.OK6K 
ESD: Dec 90 		ECD: Jan 91 	Total Cost: 48.3 
Status: To CENTCOM 13 Dec 90 for Saudi funding of equipment rental, 
	and Awaiting availability of revetments. 
 
13. DHAH 91-003, Construct Hot Pit Refueling Pad, Dhahran, S.A. 
 
	- Scope: Construct an asphalt refueling area 72m x 16m w/concrete 
	  pads for A/C parking. 
 
Funded Cost: $38K 		Unfunded Cost: $7K 
Start Date: 7 Dec 90 	ECD: 20 Dec 
Status: 50%, 2 of 3 pits complete, 3rd under construction. 
 
14. ALDH 91-0011, Construct K-Span (3-Munitions) 
 
	- Scope: 
 
Funded Cost: 				Unfunded Cost: 
ESD: 
Status: Planning 
 
15. USAR 91-0009, Constr Patriot Berms US Army, Riyadh AB, B.A. 
 
	- Scope: Construct protective berms around Patriot Missile Battery. 
 
Funded Cost: 				Unfunded Cost: 
ESD: 
Status: 25% complete. On-hold, User reconfiguring battery.