12. JEDD 910004 (AF 2) Improve Apron 12 Acces' Road, Jeddah, SA 
Scope:   Improve  ,800 ft of access road. 
Labor: Contract 
Funding Source: Saudi 					Total Cost: $95K 
ESD: Jan 91 						ECD: Jan 91 
Status: Approved, at MEAPO, 24 Dec 90 under design. Then to 
Saudi Contracting. 
Site POC:	 [(b)(2)] 
 
13. JEDD 910005 (AF 713) Replace Taxiway Lights, Jeddah SA 
Scope:   Remove and replace 351 taxiway lights with new 
	flush-mounted lights. 
Labor: Prime BEEF 
Funding Source: Saudi 					Total Cost: 0390K 
ESD: 10 Jan 91 						ECD: 20 Jan 91 
Status:    Approved by DCINC, awaiting materials from Saudis. 
	US mat'ls, due in 15 Feb 91 (8 weeks) Site POC:
[(b)(2)] 
 
14. JEDD 910100 (AF 750A) New Airfield Taxiway, Jeddah, SA. 
Scope: Construct 180 meter taxiway including turns with 
shoulders. 
Labor: Contract 
Funding Source: Saudi 
Funded Cost: $1,150K 
ESD: TBD						ECD: TBD 
Status: CENTCOM approved l0 Jan 91. To MEAPO 13 Jan 91. 
Site POC:   [(b)(2)] 
 
15. JEDD 910101 (AF 750B) Reconstruct Road N4 to Apron 16, Jeddah, 
SA
Scope:   Reconstruct 6,300' road, 20' wide, 3" asphalt on 10" 
gravel base. 
Labor: Contract 
Funding Source: Saudi 
Funded Cost: $320K 
ESD: TBD						ECD: TBD 
Status: CENTCOM approved 10 Jan 91. To MEAPO 13 Jan 91 
Site POC:   [(b)(2)] 
 
16. JEDD 910102 (AF 750C) Supply Storage Area, Jeddah, SA. 
Scope:   Construct 120'x240' asphalt open storage pad, 24'x900' 
	oad for tractor trailers. 
Labor: Contract 
Funding Source: Saudi 
Funded Cost:   $230K 
ESD: TBD 						ECD: TBD 
Status: CENTCOM approved 10 Jan 91. To MEAPO 13 Jan 91 
Site POC:	[(b)(2)]