Document Page: First | Prev | Next | All | Image | This Release | Search

File: aaaxx_42.txt
Page: 42
Total Pages: 42

PRIME BEEF AND CONTRACT COMPLETED CONSTRUCTION PROJECTS

1. ALKH 91-OOOlB (AF 742) Construct Building Foundations A1 Kharj, SA
Scope: Construct Building Foundations for K-Spans in the
Munitions Depot area.
Labor: Contract
Funding Source: Saudi				Total Cost: $27.4K
ASD: 15 Dec 90					ACD: 10 Jan 91
Status: Complete
Site POC:    [(b)(2)]

2. DHAH 91-0100 (AF 743) Aeromedical Aircraft Parking Area, Dhahran,
SA
Scope: Construct 912ft X 210ft aircraft parking area to permit
airlift of injured personnel directly from the ASF.
Labor: Contract
Funding Source: Saudi				Total Cost: $479K
ESD: Jan 91					ECD: Feb 91
Status: Canceled by user.
Site POC: 	[(b)(2)]

3. JEDD 910003 (AF 711) Construct Fuel Bladder Access Roads, Jeddah,
SA
Scope: Construct 5,000 ft acces road and 1,000 ft access road.
Improve 3,000 ft access road.
Labor: Contract
Funding Source: Saudi 				Total Cost: $690K
ESD: Jan 91 					ECD: Jan 91
Status: Approved by DCINC, MEAPO doing SOW. Canceled by user, 1
	Jan 91.	
Site POC: [(b)(2)]

4. KFIA 91-0008 (AF 700) Revetment Erection, King Fahd International	
Airport, SA.
Scope: Erect approx 140 B-1 revetment kits for TFW (Materials
and equipment purchased)
Labor: Prime BEEF
Funding Source:
Funded Cost: $68K 		Unfunded Cost: $30K 		Total Costs: $372K
ASD: 8 Dec 90						ACD: 5 Jan 91
Status: 100%, 140 kits up.
Site POC: [(b)(2)]

Document Page: First | Prev | Next | All | Image | This Release | Search