24.  SHAI  91 0012 .(AF 704) Construct Taxiway/Hardstand, Shaikh Isa AB,  
Bahrain  
  
-Scope: Phase 1 - 22,300 square meters 6" asphalt, 9,300 square  
	meters 8" concrete.  
Phase 2 - 40,800 square meters 6" asphalt, 9,300 square  
	meters B" concrete.  
Funded Cost:	$2,300K unfunded Cost: $58l.5K	Total Cost: $2,88l.5K  
Funding Source: GOJ  
ASD: Phase 1 - 12 Nov 90 ACD: 5 Jan 91  
ASD: Phase 1I - 1 Jan 91 ECD: 15 Mar 91  
Status: Phase I - 100%  Phase II - 65%,  
  
25. SHAI  91-0013 (AF 000) Construct K-Span Maintenance Building, Shaikh  
Isa AB, Bahrain  
  
- Scope: Construct 1 vehicle maintenance facility.  
  
Funded Cost: $306.1K 	Unfunded Cost: $87.2K 		Total Cost: $393.3K  
Funding Source: GOJ  
ESD: TBD 				ECD: TBD  
Status: To CENTCOM 15 Feb 91. 
 
  
26. TAB 91-0003, Supervise Revetment Erection, Tabuk AB, S.A.  
- Scope: Erect 6 B-1 revetment kits. No evaluation complete. RED  
HORSE to supervise and train user.  
  
Funded Cost: TBD Unfunded Cost: TBD	Total Cost: TBD  
Funding Source: Saudi  
ESD: TBD	ECD: TBD				 Status: On bold -  
awaiting revetment material.  
  
27. USAR 91-0010 (AR-097D) Helicopter Maintenance K-span, South Riyadh  
Airport, S.A.'  
- Scope: Construct one 60' x 120' K-Span with concrete floor and  
lighting.  
  
Funded Cost: TBD 		Unfunded Cost: TBD	Total Cost: TBD  
ESD: TBD	ECD: TBD  
Status: Awaiting 1391. 
 
  
AS OF: 16 FEB 91  