Document Page: First | Prev | Next | All | Image | This Release | Search
File: aaanx_01.txt
SUBJECT: 1706 AREFWP ENGINEERING/FIRE PROTECTION/STATUS
TO: DE DATE: 02-15-91
LGX TIME: 08:34
CC:
SUBJECT: 141030ZFEB91 1706 AREFWP/DE
PRIORITY:
ATTACHMENTS:
----------------------------------------------------------------------------------------
RAASZYUW RHIDFKA03 0461128- -RHDIBFF.
ZNY
R 141030Z FEB 91
FM 1706 AREFWP//DE//
TO RHIUFAA/HQ USCENTAF FWD//DE/LG//
INFO RUCUAAA/HQ SAC OFFUTT AFB NE//SBS/DER/LG//
RHDIAAA/HQ USCENTAF LANGLEY AFB VA//DE/LG//
BT
SUBJECT: ENGINEERING/FIRE PROTECTION/STATUS
1. (U) ENGINEERING
A. PRIME BEEF:
CURRENT: 57 PERSONNEL
PROJECTED: 3 (1 EXTERIOR, 1 INTERIOR, AND 1 CARPENTER)
B. WATER STATUS:
INSTALLED. WE ARE CURRENTLY DOING BULK CHLORINATION TO MAKE
WATER POTABLE BUT STILL WAITING ON SUPPORT KIT FOR ROWPU.
TWO SMFTS ARE STILL IN TRANSIT AND LOCATION IS UNKNOWN.
QTY/DAY LOCAL: BOTTLE DRINKING WATER UNLIMITED.
DIST SYS STATUS: INSTALLED
TREATMENT STATUS: INSTALLED FILTERS ON ORDER.
ROWPU: ONE ON SITE/NOT OPERATIONAL
PAGE 2 RHIDFKA0183
ERD STATUS: NOT REQ'D
STORAGE CAPACITY: SEVEN 20 KGAL BLADDERS ON SITE AND INSTALLED.
SANITARY
LOCAL SYS: NOT AVAILABLE
FIELD SYS: FOUR FIELD UNITS/INSTALLED/OPERATIONAL
SHOWER/SHAVE STATUS: 4 INSTALLED/OPERATIONAL
LOCAL SYS AVAIL/QTY: NONE
WASTE MGMT SYS: LAGOON CONSTRUCTED. DISTRIBUTION SYSTEM
COMPLETE.
C. POWER STATUS: HIGH VOLTAGE SYSTEM IS OPERATIONAL
IN TENT CITY AND IN OPERATIONS BUNKER AREA. POWER PLANT
OPERATION 24 HOURS/DAY AND WE HAVE PEAKED DURING EARLY MORNING
HOURS AT 1380KW.
COMMERCIAL AVAIL/CAP: NONE
DISTRIBUTION SYS CAP: INSTALLED/OPERATIONAL.
GENERATOR QTY/CAP: 3 EA 5 KW, 7 EA 60 KW, 8 EA 100 KW, 4 EA
750 KW. WAITING ON REPLACEMENT FAN BOLTS FOR 1 EA 750 KW
GENERATOR. 3 FAN BOLT SETS ARRIVED THIS WEEK.
D. ATH HOSP STATUS: NO CHANGE FROM PREVIOUS SITREP.
E. (U) VEHICLE STATUS: 1 EA M-35; 3 USAF 4X4 P.U. IN USE.
PAGE 3 RHIDFKA0183
Document Page: First | Prev | Next | All | Image | This Release | Search