         PRIME BEEF AND CONTRACT CONSTRUCTION PROJECTS
                    
         l. ALDH 91-0006 Install Commercial Power, Al Dhafra, U.A.E.
         
            Scope: Install commercial power to tent city.
            Labor: H/N contract, Bechtell, cost plus.
            Funding Source: UAE                Total Cost: $300K
            ESD:  27 Jan 91                         ECD:  31 Aug 91
            Status: Contractor ready to begin.
            
         2.  ALKH 91-0004 (AF 716) Beddown Fighter Wing, Al Kharj, SA
         
     	Scope: Obtain rental equipment to construct a beddown site to
            	support USAF flying operations. Scope is increased to
              support 5100 people.
             Labor: Military
             Funding Source: Saudi         Total Cost: $90K
             ASD: 1 Dec 90                     ECD: 31 Jan 91
             Status: 90% Progressing well. RED HORSE work completed (20 Nov -
                      27 Dec 90).
             Site POC: [(b)(2)]
         
         3. ALKH 91-0004A (AF 729) Construct Beddown Facilities, Al Kharj, SA
         
     	Scope:  Lease 179 - 12' X 39' and 20 - 24' X 39' trailers.
             Provide concrete, cable and other construction materials.
            	Labor: Contract
            	Funding Source: Saudi              Total Cost: (est) $2,082.7K
            	ESD:  31 Dec 90                     ECD:  15 Feb 91
            	Status: Approved by DCINC CENTCOM, Dec 90. 12 Jan 91 Ltr sent to
            	Gen Khalid for Saudis to contract
            	Site POC:      [(b)(2)]
            
            
         4. ALKH 91-0004B (AF 730) Erect Bare Base Cantonment Area, Al Kharj,
         
            	Scope: Construct asphalt roads and erect fencing
             Labor: Contract
             Funding Source: Saudi              Total Cost: $2,925K
             ASD: 23 Dec 90 (Roads)             ECD: 15 Feb 91
             Status: 60% Progressing.
             ESD: Jan 91 (Fence)                ECD: 15 Mar 91
             Status: CENTCOM following up. Work has not started.
             Site POC: [(b)(2)]
         
      5. ALKH 91-0004C (AF 732) Water Distribution, Al Kharj, SA
         Scope: Purchase water well pumps for beddown camp non potable
                     water.
         
             Labor: Contract
             Funding Source: Saudi              Total Cost: $52K
             ESD: 31 Dec 90                     ECD: 31 Dec 90
             Status:  Saudis disapproved.  4 TFW/DE to rejustify to MODA.
             Site POC:  [(b)(2)]        
         
         6.  BATE 910100 (AF 756) Facility  Hardening, Bateen, UAE
             Scope: Construct protective revetments for key facilities
                        (oil drums filled with sand)
             Labor: Prime BEEF
             Funding Source: GOJ                Total Cost: $33.OK
             ESD:      TBD                           ECD: TBD
             Status: Awaiting CENTCOM material order. CENTCOM considering
             Concrete.
         