7. CAIR 91-0003 (AF 762?) Alter-Repair Ramp, Cairo, Egypt
Scope: Construct new concrete pad over existing asphalt and
concrete ramp.
Labor: Contract
Funding Soruce: GOJ Total Cost: $883.9K
ESD: TBD ECD: TBD
Status: To CENTCOM on 23 Jan 91.
Site POC: [(b)(2)]
8. DHAH 91-0011 (AF 735) Construct Squadron Ops Facility, Dhahran,
SA.
Scope: Construct 7m x 2m squadron operations facility.
Labor: Contract Total Cost: $480K
ESD: TBD ECD: TBD
Status: Awaiting siting approval.
9. DHAH 91-0011 (AF 736) Aircraft Parking Areas, Dhahran SA
Scope: Construct 30 concrete aircraft parking pads with grounding
rods. 15cm X 25n X 24m
Labor: Contract
Funding Source: Saudi Total Cost: $480K
ESD: Jan 91 ECD: Feb 91
Status: 100% designed. To Saudis 12 Jan 91 to contract.
Site POC: [(b)(2)]
10. DHAH 91-0013 (AF 738) Construct MAC Ops Storage Yard, Dhahran, SA
Scope: Install 160 meters of chain link fence and install four
400 watt floodlights
Labor: Contract
Funding Source: Saudi
ESD: TBD ECD: TBD
Status: CENTCOM validating.
Site POC: [(b)(2)]
11. DHAH 91-0317 (AF 757) Upgrade Survivability, Dhahran, SA.
Scope: Rent equipment for constructing berms, ditches, bunkers,
etc., for 45 days.
Labor: Prime BEEF
Funding Source: Saudi Total Cost: $106.8K
ESD: Jan 91 ECD: Mar 91
Status: Equip delivery started 23 Jan.
Site POC: [(b)(2)]
12. DOHA 91-0004 (AF 714), Install Concrete Tent Floors, Doha IAP,
Qatar.
Scope: Install 1,000 8' X 10' X 4' precase concrete slabs to
replace deteriorating fabric flooring for all tents.
Labor: Prime BEEF
Funding Source: GOJ Total Cost: $150K
ESD: Jan 91 ECD: Jan 91
Status: Approved by CENTCOM Dec 90. Awaiting GOJ contract.