    13.  DOHA 91-0015 (AF 15), Erect Survival Recovery Center (SRC), Doha
         IAP, Qatar.
         Scope:  Erect 12m X 25m pre-cast reinforced panel building with
         	          poured concrete footings and floor slab for SRC.
         Labor:  Prime BEEF Site Rep.  Contract building erection
         Funding Source:  GOJ               Total Cost:  $78,500
         ESD:  l Jan 91                     	    ECD:  20 Jan 91
         Status:   Awaiting GOJ contract.
         Site POC:    [(b)(2)] 
         
    14.  JEDD 910004 (AF 712) Improve Apron 12 Access Road, Jeddah, SA
         Scope:  Improve 4,800 ft of access road.
         Labor:  Contract
         Funding Source:  Saudi             Total Cost:  $95K
         ESD:  Jan 91                             ECD:  Jan 91
         Status:  Approved, at MEAPO, 24 Dec 90 under design.  Then to
         Saudi Contracting.
         Site POC:      [(b)(2)]
         
    15. JEDD 910005 (AF 713) Replace Taxiway Lights, Jeddah SA
         Scope:  Remove and replace 351 taxiway lights with new
         		flush-mounted lights.
         Labor:  Prime BEEF
         Funding Source:  Saudi             Total Cost:  $360K
         ESD:  1 Mar 91                         ECD:  15 Mar 91
         Status:  Approved by DCINC, awaiting materials from Saudis.
         	        US mat'ls, due in 15 Feb 91 (8 weeks)
         Site POC:       [(b)(2)]
                
    16.  JEDD 910100 (AF 750A) New Airfield Taxiway, Jeddah, SA.
         Scope:  Construct 180 meter taxiway including turns with
         shoulders.
              Labor: Contract
              Funding Source: Saudi
              Funded Cost: $1,150K
              ESD: TBD               ECD: TBD
              Status:  100% design 22 Jan.
              Site POC:        [(b)(2)]
         
    17.  JEDD 910101 (AF 750B) Reconstruct Road N4 to Apron 16, Jeddah,
         SA.
         Scope:  Reconstruct 6,300' road, 20' wide, 3" asphalt on lO"
         gravel base.
         Labor: Contract
         Funding Source: Saudi
         Funded Cost: $32OK
         ESD: TBD           ECD: TBD
         Status:  100% design 22 Jan.
         Site POC:      [(b)(2)]
         
    18.  JEDD 910102 (AF 750C) Supply Storage Area, Jeddah, SA.
         Scope:  Construct 120'x240' asphalt open storage pad, 24'x900'
         road for tractor trailers.
         Labor:  Contract
         Funding Source:  Saudi
         Funded Cost:  $230K
         ESD:  TBD               ECD:  TBD
         Status:  100% design 22 Jan.
         Site POC:     [(b)(2)]
         