    19.  JEDD 910103 (AF ) Improve Airfield Road, Jeddah, SA.
         Scope:  Improve 27'x11,000' road with 1" asphalt leveling coat
         and 3" top coat.
         Labor: Contract
         Funding Source: Saudi
         Funded Cost: $280K
         ESD: TBD            ECD: TBD
         Status:  100% design 22 Jan 91.
         Site POC:      [(b)(2)] .
         
    20.  JEDD 910104 (AF 754) Move Airfield Taxiway Signs, Jeddah, SA
         Scope:  Construct 28 new airfield sign supports and move old
         signs out further to new supports.
         Labor:  Contract
         Funding Source:  Saudi
         Funded Cost:  $4OK
         ESD:  TBD             ECD:  TBD
         Status:  14 Jan back to CENTAF.  Need to get back to CENTCOM.
         Site POC:     [(b)(2)]
         
    21. KFIA 91-0100 (SC-004), SOCCENT Temporary Housing, King Fahd
         International Airport, SA.
         Scope:  Purchase, deliver, erect facilities for SOCCENT Billeting
         messing, MWR (84 trailers, 500 PN dining facility).
         SOCCENT moving out of contractor's facilities.
         Labor:  Contract
         Funding Source:  Saudi             Total Cost:  2,137.6K
         ESD:  3 Feb 91                          ECD:  3 Mar 91
         Status:  NTP granted to buy trailers and dining hall.
         Site POC:      [(b)(2)]
         
    22.  KFIA 91-0101 (AF-758), Pave helopad, King Fahd International
         Airport, SA.
         Scope:  Construct 150m x 400m area for helocopter parking.
         Labor: Contract
         Funding Source: Saudi        Total Cost: $180K
         ESD: TBD                          ECD: TBD
         Status: CENTCOM validating.
         Site POC: [(b)(2)]
         
         
    23.  KFIA 91-0102 Construct Dog Kennel, King Fahd International
          Airport, SA.
          Scope:  Construct dog kennel with concrete slab, drain and fence.
          Labor: Contract
          Funding Source: Saudi        Total Cost: $5.l K
          ESD: TBD                           ECD. TBD
          Status: Passed to Saudis.
          Site POC: [(b)(2)]
         
    24.  KFIA 91-0103 Pave Parking Area, King Fahd International Airport,
           SA.
           Scope:  Pave 15m x 70m vehicle parking area.
           Labor: Contract
           Funding Source: Saudi        Total Cost: $3.lK
           ESD: TBD                           ECD: TBD
           Status: Passed to Saudis.
           Site POC:   [(b)(2)]
         

Document Page: First | Prev | Next | All | Image | This Release | Search