        25.  KFIA 91-0104 Pave Parking Lot, King Fahd International Airport,
        SA. 
        Scope:  Construct asphalt parking area for vehicles - SOCCENT
                     area.
              Labor: Contract
              Funding Source: Saudi         Total Cost: $25.7K
              ESD: TBD                      ECD: TBD
              Status: Passed to Saudis.
              Site POC: [(b)(2)]
         
         26.  KFIA 91-0105 Camp Upgrade, King Fahd International Airport, SA.
              Scope:  Construct tent floors, doors and items essential to
                           mission accomplishment.
              Labor: Prime BEEF
              Funding Source: Saudi         Total Cost: $48.OK
              ESD: TBD                      ECD: TBD
              Status: Saudis approved 20 Jan 91.
              Site POC: [(b)(2)]
         
    27.  KFIA 91-0201 (SC-003), Covered Aircraft Storage, King Fahd
         International Airport, SA.                
         Scope:  Purchase and erect relocatable aircraft shelters
         (3 sprung structures with clamshell doors, 21,600 SF).
         Labor: Prime BEEF
         Funding Source:  GOJ               Total Cost:  $752K
         ASD:  15 Dec 90                        ECD:  10 Feb 91
         Status:  Sprung structures 50% complete. One sprung up, frame up.
         Contractor left due to war.  Prime BEEF finishing two.
         Need help on third one.  On hold due to war.
         Site POC:    [(b)(2)]
         
    28.  KKIA 91-0001 (AF 733) Install Commercial Power, King Khalid
           International Airport, SA
           Scope:  Install commercial power to Air Transportable Hospital,
           communications site and tent city.
             Labor: Prime BEEF
             Funding Source: Saudi    Total Cost: $43.3K
             ASD: 15 Jan 91           ECD: 26 Jan 91
             Status: 90% complete.
             Site POC: [(b)(2)]
         
    29.  KKMC 91-0001 (AF 727) Erect Bare Base Cantonment Area, King
           Khalid Military City, SA.
           Scope:  Erect bare base cantonment area - includes select fill,
           lumber, concrete, gravel and rental equipment.
           Labor:  Prime BEEF
           Funded Cost:  $88K   Unfunded Cost:  $25.5K  Total Cost:  $113.5K
           ESD:  29 Dec 90               ECD:  31 Jan 91
           Status:  50% complete.  Awaiting revised scope.
           Site POC:      [(b)(2)]
         
    30.  KKMC 91-OOOlA (AF 739) Pave Roads, King Khalid Military City, SA
           Scope:  Construct two asphalt roads for dust control
           Labor: Contract
           Funding Source: Saudi    Total Cost: $65.8
           ESD: 15 Feb 91           ECD: 1 Mar 91
           Status: At MEAPO for design.
           Site POC: - [(b)(2)]
         