RED HORSE Construction Projects

1.	ALKH 91-0001, Construct Munitions Storage Area, Al Kharj AB, S. A.

	-Scope:  Construct 12 ea 50x100 and 5 ea 50x50 K-Spans, buiild 14
	   miles of munitions storage roads (clay), and pave 1.6 miles of 
 	   access road.
	-7,410 meter chain link fence by contract.

Funded Cost:   $1,664.9					Unfunded Cost:  #306.9K
ECD:	31 Jan 91
	Clay Roads 15 Dec 91 50% complete; Asphalt Roads:  Contract Awarded;
	Fence Contract 5% complete
Status:	5-50 x 100 and 4-15 x 50 K-Spans up.  Building on hold for
	steel.

2.	ALKH 91-004, Beddown TFW, Al Kharj AB, S. A.

	- Scope:  Beddown 3800 man tent city and 114 aircraft

Cost:	Funded $34.4		Unfunded Cost:  N/A
ECD:	15 jan 91 (Cantonment Area)
Status:	45%

3.	ALKH 91-007, Construct TFW Maint K-Spans (4), Al Kharj AB S.A.

	-Scope:  2 - 50�x80� K-Spans with end walls, lights, Conc, floors.
	2 - 50� x 80� erected.  Awaiting Steel for 2 - 50� x 100� K-Spans.

4.	KFIA 91-0008, Supervise Revetment Erection, King Fahd IAP, S. A.

	- Scope:  Erect approximately 140 B-1 revetment kits for TFW.
		Will supervise/train for 30 days the turn over to BCE.

Funded Cost:  $68K				Unfunded Cost:  $304K
ECD:  30 Jan 91
Status:  40 kits up of 140.  Working to accellerate construction to move
ECD to Jan 91.

5.	CAIR 91-0002, Pave Roads/Airfield Shoulders, Cairo West AB, Egypt

	-Scope:  Construct 2-inch thick asphalt pavement over compacted base,
	22,200 square meters.

Funded Cost:  $81.3				Unfunded Cost:  $56.2K
ESD:  N/A
Status:  Cancelled by BCE