6.	SHAI 19-0012, Construct Taxiway/Hardstands, Shaikh Isa AB, Bahrain

	Scope:  Phase 1 - 22,300 square meters 6� asphalt, 9,300 square
		meters 8� concrets.
		Phase 2 - 40,800 square meters 6� asphalt, 9,300 square
		meters 8� concrete

Funded Cost:  $2,300L			Unfunded Cost:  581.5K
ECD:  15 Jan 91; Phase 1:  1 Jan 91;  Phase II:  15 Jan 91
Status:  Phase I - 26%

7.	ALMI 91-0012, Construct Aircraft Parking Ramp, Al Minhad AB, U.A. E.

	- Scope:	Construct a 500� x 1000� asphalt and concrete parking apron.
		(Follow-on revetment project ALMI91-0004).

Funded Cost:  $815.6K				Unfunded Cost:  $493.5K
ECD:  8 Jan 91
Status:  Started with U.S. funded rental equip & materials.
	GOJ funding for rental/materials approved.

8.	USMC 91-0001, Construct 6 K-Spans, Al Jubayl, S. A.
	
	-Scope:  Construct 6 ea 60x80 K-Spans for helicopter maintenance
	facilities and train Seabees.  No evaluation.

Start Date:  7 Dec 90			ECD:  15 Jan 91
Status:	3 of 6 K-Spans complete

9.	KKMC 91-0001A, Beddown Construction, King Khalid Military City, S..A.

	Scope:	Construct 2 asphalt pads for dust control (24�x 2600�x 2�
	and 12�x 3600�x 2�).
Funded Cost:  $65.8 K		Unfunded Cost:  Unk		Total Cost:  Unk
ESD:  Unk
Status:  To CENTCOM Dec 90 for Saudi contract accomplishment

10.	KKMC 91-0002 Construct A-10 Rearm and Maint Area, King Khalid 
Military

	-Scope:  Construct two asphalt pads 100� x 1000� for A-10 Rearm area
	and hard broke maintenance area, parallel to existing taxiway.
	Construct by contract.

Funded Cost: 98.7K		Unfunded Cost 10L		Total Cost:  $108.7K
ESD:  Dec 90		ECD:  Jan 91
Status:  To CENTCOM 13 Dec for Sauidi Funding & Contract.