11.	KKMC 91-0003, Supervise Revetment Erection, King Khalid Military
City, S. A.

	-Scope:  Erect and fill 1 ea, B-1 revetment kit.  RED HORSE to
	Supervise and train user.

Funded Cost:  18.3K					Unfunded Cost 30.0K
ESD:  Dec 90		ECD:  Jan 91		Total Cost 48.3 K
Status:  To CENTCOM 13 Dec 90 for Saudi Funding of equipment rental,
	and awaiting availability of revetments.

12.	DHAH 91-003, Construct Hot Pit Refueling Pad, Dhahran, s.A.

	-Scope:  Construct an asphalt refueling area 72m x 16m w/concrete
	pads for A/C parking

Funded Cost:  $38K			Unfunded Cost:  $7K
Start Date:  7 Dec 90		ECD:  25 Dec
Status:  85%, 2 of 3 pits coplete, 3rd under construction.

13.	ALDH 91-0011, Construct K-Span (3-Munitions)

	-Scope:
Funded Cost:					Unfunded Cost:
ESD:
Status:  Planning

14.	USAR 91-0009, Constr Patriot Berms US Army, Riyadh AB, S.A.

	-Scope:  Construct protective berms around Patriot Missile Battery.

Funded Cost:  0			Unfunded Cost:
ESD:  13 Dec 90		ECD:  24 Dec 90
Status:  45% complete.  New plan under construction

15.	USAR 91-0010, Constr Transient Heliport, Eskan Village for US Army,
	Riyadh, S. A.

	-Scope:  Construct 200� x 2000� Asphalt heliport.

Funded Cost:  $62K		Unfunded Cost:
ESD:  24 Dec 90			ECD:
Status:  Planning.  Army clearing site 16 Dec 90.  RH checking materials
for DD Form 1391.  Hold.  Awaiting CENTCOM direction.

16.	DOHA 91-0010,  Construct Rations Storage Facility, Doha, Qatar

	-Scope:  Construct 50�x100� K-Span facility with insulation and air
	conditioning.

Funded Cost:  $112.4K			Unfunded Cost:  $84.7K
ESD:  15 Feb 91
Status:  Awaiting HN siting approval