USCENTAF/DE
POWER PLANTS - 750 KW GENERATORS
ELEC ASSETS 750 KW
LOCATION FOR POP OF IN USE STATUS LIMFACS/COMMENTS
AL AYN 1200 4 SAT
AL DHAFRA 2500 7 SAT
AL KHARJ 4400 0 NOT RATED NOTE 1
AL MINHAD 950 3 MAR NOTE 2
BATEEN 1100 3 SAT
CAIRO 1100 3 SAT
DHAHRAN 1200 2 MAR NOTE 3
DOHA 1000 3 SAT
JEDDAH 0 0 SAT NOTE 4
KHAMIS 0 0 SAT NOT REQUIRED
K. FAHD 4400 8 SAT NOTE 5
K. KHALID 400 0 MAR NOTE 6
MASIRAH 1000 2 SAT
RIYADH 850 4 SAT
SEEB 1500 2 SAT
SHAIKH ISA 1500 3 MAR NOTE 7
SHARJAH 400 2 SAT
TABUK 0 0 SAT NOT REQUIRED
TAIF 1150 5 SAT
THUMRAIT 2650 7 SAT
TOTAL 28730 58
GOAL: CONNECT TO COMMERCIAL POWER. RETAIN ORGANIC ASSETS FOR BACK-UP.
NOTE 1: AWAITING HOST NATION APPROVAL TO START BUILDING CAMP FOR 4400
PERSONNEL. 14 SOLAR GENERATORS PROGRAMMED FOR THIS SITE. THIS WILL
BE THE FIRST LARGE SCALE USE OF SOLARS IN SWA FOR DESERT SHIELD.
REMAINING 5 SOLARS WILL BE WITH CEMIRT AT THUMRAIT AS SPARE FOR THIS
SITE.
NOTE 2: SITE BORROWED A HOST NATION FUEL TRUCK TO SUPPLY FUEL TO 750'S. STILL
AWAITING FUEL BLADDERS SUPPOSEDLY SOURCED BY LG. THEY HAVE BEEN
WAITING OVER SIX WEEKS NOW. LG UNABLE TO SUPPLY US WITH PROJECTED
DELIVERY DATE.
NOTE 3: 750KW DIESEL GENERATOR SHIPPED TO THUMRAIT FOR REPAIR OF SEIZED
ENGINE.
NOTE 4: FOUR DIESEL 750'S HELD AT THUMRAIT BY LG TO FILL POTENTIAL 1,500
POPULATION CAMP. CEMIRT DEPLOYED TO SITE TO HELP DETERMINE ELECTRICAL
EQUIPMENT REQUIRED TO FILL THEIR NEEDS. CURRENTLY UNABLE TO MEET
POWER DEMAND. BCE IS WILLING TO WAIT UP TO 6 MONTHS TO ACHIEVE A
COMMERCIAL POWER TIE-IN. HE DOES NOT WANT ADDITIONAL GENERATORS OR
HIGH VOLTAGE.