USCENTAF/DE 
POWER PLANTS - 750 KW GENERATORS 
 
		ELEC ASSETS 	750 KW 
LOCATION	FOR POP OF	IN USE		STATUS	 LIMFACS/COMMENTS 
 
AL AYN	1200		4		 SAT 
AL DHAFRA	2500		7		 SAT 
AL KHARJ	4400		0		 NOT RATED 	NOTE 1 
AL MINHAD	950		3		 MAR		NOTE 2 
BATEEN	1100		3		 SAT 
CAIRO		1100		3		 SAT 
DHAHRAN	1200		2		 MAR		NOTE 3 
DOHA		1000		3		 SAT 
JEDDAH	0		0		 SAT		NOTE 4 
KHAMIS	0		0		 SAT		NOT REQUIRED 
K. FAHD	4400		8		 SAT		NOTE 5 
K. KHALID	400		0		 MAR		NOTE 6 
MASIRAH	1000		2		 SAT 
RIYADH	850		4		 SAT 
SEEB		1500		2		 SAT 
SHAIKH ISA	1500		3		 MAR		NOTE 7 
SHARJAH	400		2		 SAT 
TABUK		 0		0		 SAT		NOT REQUIRED 
TAIF		1150		5		 SAT 
THUMRAIT	2650		7		 SAT
 
TOTAL		28730		58 
 
GOAL: CONNECT TO COMMERCIAL POWER. RETAIN ORGANIC ASSETS FOR BACK-UP.
 
NOTE 1: AWAITING HOST NATION APPROVAL TO START BUILDING CAMP FOR 4400 
	PERSONNEL. 14 SOLAR GENERATORS PROGRAMMED FOR THIS SITE. THIS WILL 
	BE THE FIRST LARGE SCALE USE OF SOLARS IN SWA FOR DESERT SHIELD. 
	REMAINING 5 SOLARS WILL BE WITH CEMIRT AT THUMRAIT AS SPARE FOR THIS 
	SITE. 
 
NOTE 2: SITE BORROWED A HOST NATION FUEL TRUCK TO SUPPLY FUEL TO 750'S. STILL 
	AWAITING FUEL BLADDERS SUPPOSEDLY SOURCED BY LG. THEY HAVE BEEN 
	WAITING OVER SIX WEEKS NOW. LG UNABLE TO SUPPLY US WITH PROJECTED 
	DELIVERY DATE. 
 
NOTE 3: 750KW DIESEL GENERATOR SHIPPED TO THUMRAIT FOR REPAIR OF SEIZED 
	 ENGINE. 
 
NOTE 4: FOUR DIESEL 750'S HELD AT THUMRAIT BY LG TO FILL POTENTIAL 1,500 
            POPULATION CAMP. CEMIRT DEPLOYED TO SITE TO HELP DETERMINE ELECTRICAL 
            EQUIPMENT REQUIRED TO FILL THEIR NEEDS. CURRENTLY UNABLE TO MEET 
            POWER DEMAND. BCE IS WILLING TO WAIT UP TO 6 MONTHS TO ACHIEVE A 
           COMMERCIAL POWER TIE-IN. HE DOES NOT WANT ADDITIONAL GENERATORS OR 
           HIGH VOLTAGE.