NOTE 6: TWO FFGM KITS ARRIVED 6 NOV 90 AND WITH ONE KIT PROGRAMMED
FOR SHIPMENT TO DHAHRAN. BRITISH ROLLED MAT SYSTEM AVAILABLE; US
BCE PERSONNEL HAVE HAD LIMITED TRAINING.

NOTE 7: LGT WORKING TO CORRECT SHORTAGE OF RRR VEHICLES. MAJOR ITEMS
INCLUDE EXCAVATORS, 8 CY DUMPS, 4 CY FELs, TRAILERS, VIBRATORY
ROLLERS, AND DOZERS. EIGHTY-TWO PRIME BEEF PERSONNEL FROM BATEEN,
DHAHRAN, DOHA, RIYADH, SHAIKH ISA, AND TABUK HAVE BEEN TRAINED ON
THE FFGM SYSTEM AND USING THE PYRAMENT SAC-PAC SPALL REPAIR
MATERIAL. FOUR MORE CLASSES WITH 12 PERSONS EACH ARE SCHEDULED
FOR DHADRAN, KING FAHD, KING KHALID INTL AIRPORT, AND RIYADH,
CONCLUDING ON 12 DEC 90. TWO ADDITIONAL CLASSES ARE PLANNED FOR
RIYADH AND KING FAHD, DEPENDING ON AVAILABILITY OF VEHICLES.

AS OF 8 DEC 90
OPR: [(b)(2)]