21. SHAI 91-0012 (AF 704, Construct Taxiway/Hardstands, Shaikh Isa AB,
Bahrain

	-Scope: Phase 1 - 22,300 square meters 6" asphalt, 9,300 square
	 meters B" concrete.
	 Phase 2 - 40,800 square meters 6" asphalt, 9,300 square
	 meters 8" concrete.

Funded Cost: $2,300K 		Unfunded Cost: $581.5K 		Total Cost: $2,881.5R
Funding Source: GOJ		
ASD: 12 NOV 90 	ECD: 15 Feb 91 	  Phase 1 ACD: 5 Jan 91; Phase II: 15 Feb
91
Status:   Phase I - 100% 		Phase II - 10%

22. SRAI 91-0013, Construct K-Span Maintanence Building, Shaikh Isa AB,
Bahrain

	- Scope: Construct 1 vehicle maintenance facility.

Funded Cost: TBD 		Unfunded Cost: TBD 		Total Cost: TBD
Funding Source: GOJ-
ESD: TBD 					ECD: TBD
Status: Under evaluation, 4 Jan 91.

23. TABU 91-0003, Supervise Revetment Erection, Tabuk AB, S.A.

	- Scope: Erect 6 B-1 revetment kits.   No evaluation complete.  RED
	  HORSE to supervise and train user.

Funded Cost: TBD		Unfunded Cost: TBD		Total Cost: TBD
Funding Source: Saudi ESD: TBD				ECD: TBD
Status: On hold - Revetments sent to KFIAP

							AS OF: 19 JAN 91
							OPR: [(b)(2)]