RED HORSB COMPLETED CONSTRUCTION PROJECTS 
 
1. ALRH 91003 (AF 716), Beddown MSS/SP Squadron, Al Kharj, SA 
 
	- Scope: Erect 7' high chain link fence; pave access roads, 
		repair electrical mechanical, HVAC systems. 
 
Funded Cost: $41.6K 		Unfunded Cost: $19.9K 		Total Cost:  $61.5K 
Funding Source: Saudi 
ASD: 15 Oct 90 					ACD: 8 Nov 90 
Status: Complete 

2. ALRH 91-0004, Beddown TFW, A1 Kharj AB, S.A. 

	- Scope: Beddown 3800 man tent city ad 114 aircraft. 
 
Funded Cost: $34.4K 		Unfunded Cost: $ K 		Total Cost: $34.4K 
Funding Source: Saudi ASD: 20 Nv 90		ACD: 28 Jan 91 
(Cantonment Area) 
Status:   RED HORSE Complete.     Prime BEEF continued project. 
 
3. ALMI 91-0010 (AF 706), Construct Hot Pit Refueling Pad, Al Minhad, 
U.A.E. 
 
	-Scope: Construct 60m x 60m x 9-inch thick concrete pad w/beamed 
	  fuel bladder area. 
 
Funded Cost: $89.8K		 Unfunded Cost:	$70.5K		Total Cost:  $160.3K 
Funding Source: GOJ 
ESD: 7 Jan 91				ACD:	15 Jan 91 
Status: 100% 
 
4. ALMI 91-0012 (AF 710), Construct Aircraft Parking Ramp, Al Minhad AB, 
U.A.E. 
 
	- Scope: Construct a 500' x 1000' asphalt and concrete parking apron. 
		(Follow-on revetment project ALMI91-0004). 
 
Funded Cost: $815.6K 		Unfunded Cost: $493.5K 		Total Cost: $1,309.1K 
Funding Source: GOJ 
ASD: 7 Dec 90 				ACD: 7 Jan 91 
Status: 100% 
 
5. DHAH 91-0003, Construct Hot Pit Refueling Pad, Dhahran, S.A. 
 
	- Scope: Construct 3 ea, asphalt refueling areas 72m X 16m "/concrete 
		pads for A/C parking. 
 
Funded Cost: $60.0K 		Unfunded Cost:	$70.0K		Total Cost:	$130.0K 
Funding Source: Saudi 
ESD: 4 Dec 90 				ACD:22 Dec 90 
Status: 100% complete.