6.  KFIA 91-0008, Supervied Revetment Erection King Fahd IAP, S. A.
	- Scope:  Erect approximately 140 B-1 revetment kits for TFW.
	Turned over to BCE.

Funded Cost:  $68.OK  Unfunded Cost:  $304.OK Total Cost $372.OK
Funding Source:  Saudi ACD:  18 Dec 90
Status:  RED  HORSSE Complete.  Prime BEEF continued project.

7.  KRMC 91-0001, cAMP bEDDOWN, kING kHALID mILITARY cITY s.a.

	-Scope:  Construct 65 man ten city.
Funded Cost:  N/A	Unfunded Cost: N/A	Total Cost: N/A
ASD: 1 Dec 90		ACD:  15 Dec 90
Status:  RED HORSE complete.  Prime BEEF continued project.

8.  RIYA 910020 (AF 000), Rehab Shoppette, Esken, SA

	-Scope:  Rehab old living quarters into shoppette complex.

Funded Cost:  $47.OK 	Unfunded Cost $13.OK	Total Cost:  $60.OK
Funding Source:  AAFES
ASD: 30 Oct 90 		ACD:  05 Dec 90
Status:  Complete

9.  RIYA 910023 (AF000), Rehab Barber Shop, Eakan, SA

	-Scope:  Rehab old living quarters inio barber shop.

Funding Cource:  AAFES
ASD:  30 Oct 90		ACD:  05 Dec 90
Status:  Complete

10.  RIYA 910029 (AF000), Upgrade RH Eskan Village, Eskan, SA

	-Scope:  Repair A/C's paint, lumber, etc.

Funded Cost:  $9.OK	Unfunded Cost:  $4.5k	Total Cost:  $13.5K
Funding Source:  Saudi
ASD:  15 Oct 90		ACD:  15 Nov 90
Status:  Complete

11.  RIYA 910035 (AF 000), Rehab Snack Bar, Eskan, SA

	-Scope:  Rehab old living quarters into Snack Bar.

Funded Cost $39.OK	Unfunded Cost:  $12.7K	Total Cost:  $51.7K
Funding Source AAFES
ASD:  30 Oct 90		ACD:  05 Dec 90
Status:  Complete	