23.   KFIA 91-0104 Pav Parking Lot, King Fahd International Airport, 
        SA. 
        Scope:   Construct asphalt parking area for vehicles - SOCCENT 
        	        area. 
        Labor: Contract 
        Funding Source: Saudi			Total Cost: $25.7K 
        ESD: TBD					ECD: TBD 
        Status: Passed to Saudis. 
        Site POC: [(b)(2)]
 
24.   KFIA 91-0105 (AF-759) Camp Upgrade, King Fahd International 
        Airport, SA. 
        Scope:   Construct tent floors, doors and items essential to 
	       mission accomplishment. 
        Labor: Prime BEEF 
        Funding Source: Saudi			Total Cost: $152.3X 
        ESD: TBD					ECD: TBD 
        Status: Passed to Saudis. 
        Site POC:   [(b)(2)] 
 
25.   KFIA 91-0201 (SC-003), Covered Aircraft Storage, King Fahd 
        International Airport, SA. 
        Scope:   Purchase and erect relocatable aircraft shelters 
	       (3 sprung structures with clamshell doors, 21,600 SF). 
        Labor: Prime BEEF 
        Funding Source: GOJ 			Total Cost: $1,023K 
        ASD: 15 Dec 90 				ECD: 15 Jan 91 
        Status: Concrete pads done 3 Jan 91. Sprung structures 50% 
	      complete. One sprung up, frame up. On hold due to war. 
        Site POC: [(b)(2)] 
 
26. KKIA 91-0001 (AF 733) Install Commercial Power, King Khalid 
International Airport, SA 
Scope: Install commercial power to Air Transportable Hospital, 
communications site and tent city. 
Labor: Prime BEEF 
Funding Source: Saudi 				Total Cost: $43.3K 
ESD: 15 Jan 91 					ECD: 30 Jan 91 
Status: Materials ordered. Due in 13 Jan 91. 
Site POC: [(b)(2)] 
 
27. KKMC 91-0001 (AF 727) Erect Bare Base Cantonment Area, King 
Khalid Military City, SA. 
Scope: Erect bare base cantonment area - includes select fill, 
lumber, concrete, gravel and rental equipment. 
Labor: Prime BEEF 
Funded Cost: $88K 		Unfunded Cost:  $25.5K T	Total Cost:  $113.5K 
ESD: 29 Dec 90 					ECD:	31 Jan 91 
Status: Waiting revised scope. 
Site POC: [(b)(2)] 
 
28. KKMC 91-000lA (AF 739) Pave Roads, King Khalid Military City, SA 
Scope: Construct two asphalt roads for dust control 
Labor: Contract 
Funding Source: Saudi				Total Cost: $65.8K	
ESD: 15 Feb 91					ECD: 1 Mar 91 
Status: At MEAPO for design. 
Site POC:	[(b)(2)]