29. KKMC 91-002A (AF 740) Construct A-10 ICT Ar~ -, King Khalid 
Military City, S.A. 
Scope: Construct asphalt A-10 aircraft integrated combat turn 
and maintenance area parallel to existing taxiway. KKMC 91-0002 
was 100'x1000', KKMC 91-002A increased scope to 100'x4000'. 
Labor: Contract materials, US Army Labor, RED HORSE. 
Funding Source: Saudi 				Total Cost: $613.0 
ASD: 8 Jan 91 					ECD: 30 Jan 91 
Status: CENTCOM approved increased scope: 30% complete. 
Asphalt contractor left due to war. RED HORSE looking for 
Asphalt. AM-2 Mat due in as back-up. Site POC: [(b)(2)] 
 
30. KKMC 91-0003 (AF 741) Erect Aircraft Revetments, King Khalid 
Military City, SA 
Scope: Erect and fill 8 B-1 aircraft revetments, rent equip. 
Labor: Military (RED HORSE supervisor) 
Funding Source: Saudi 				Total Cost: $96K 
ASD: 15 Jan 91 					ECD: 31 Jan 91 
Status: 5% complete, CENTCOM placing material orders. 
Site POC: [(b)(2)] 			Riyadh MODA POC:  [(b)(2)] 

31. RIYA 91-0004 (AF 701) Commercial Power USMTM/RSAF, Riyadh AB, SA 
Scope: Install underground commercial power to USMTM and RSAF 
areas to include transformers, disconnects and double 
throw switches. 
Labor: Contract 
Funding Source: Saudi 				Total Cost: $309K 
ESD: Jan 91 					ECD: Feb 91 
Status: Awarded 6 Jan 91. RED HORSE providing updated design to 
Saudi contractor. 
Site POC:	[(b)(2)] 			RH POC:    [(b)(2)] 
 
32. RIYA 91-0028 (AF 038) Repair Ramp, Riyadh AB, SA 
Scope: Repair Failing asphalt by replacement. 
Labor: Contract 
Funding Source: Saudi				Total Cost: $941K 
ASD: 25 Dec 90					ECD: 15 Feb 91 
Status: 70% complete. 
Site POC: 	[(b)(2)] 
 
33. RIYA 91-00033 (AF 015) Expand Ramp, Riyedh AB, SA 
Scope: Expand existing apron. 
Labor: Contract 
Funding Source: Saudi				Total Cost $7, 500K 
ASD: 30 Dec 90					ECD: 15 Feb 91 
Status: 50% complete 
Site POC: 	[(b)(2)] 
 
34. RIYA910101 (AF 755) Partiot Site Commercial Power, Riyadh SA 
Scope: Install commercial power to patriot missile site. 
Labor: Contract 
Funding  Source: Saudi 				Total Cost: $48.5K 
ESD: TBD 					ECD: TBD 
Status: Riyadh_AB/DE getting detailed quotes. 
Site POC: 	[(b)(2)]