Document Page: First | Prev | Next | All | Image | This Release | Search
File: aacep_13.txt
13
each commander had his or her own set of priorities.
The priorities for engineers upon arrival varied from site to
site' depending on what was available. The overall guidance was
set by the deployed wing and combat support element commanders
based upon inputs from Engineering and Services personnel.
At a bare base beddown, engineers were responsible for several
operational concerns such as aircraft arresting barriers' airfield
lighting, runway sweeping' and fuel storage. The most common
arresting barrier was the BAK-12 system. This consisted of two
rotary friction energy absorbers joined across the runway by a hook
-cable or by a nylon barricade net. Engineers installed the BAK-12
by either bolting each absorber to a concrete pad for surface
installation or in a concrete pit for below grade installation.
Nine of the sites used the BAK-12. Another type of barrier was the
mobile aircraft arresting system (MASS)' which provided for rapid
deployment of aircraft recovery capability' enabling high cycle
arrestment of hook-equipped tactical aircraft or bomb damaged
planes on redundant surfaces in a postattack environment. It was
easily transportable and could be set up on various types of
surfaces. Fight sites received a MAAS, but only half that number
actually installed them.
Airfield lighting was not a major problem at most of the
initial beddown locations. Because they had existing flying
missions at the sites' adequate approach and runway lighting was in
place. The exception was A1 Ayn. The airfield was under
construction for use by the royal family. There was no airfield
lighting on the site. This created difficulties in the early days
and weeks of the deployment. Aircraft loaded with equipment and
Harvest Falcon assets for the site were often unable to locate the
airfield after dark. They went to A1 Dhafra, the nearest base, and
unloaded their cargo there. Of course, many times this cargo never
made it to A1 Ayn. After several days, the Scott AFB engineers
received and pieced together two 5,000-foot Harvest Falcon lighting
sets for a 13,000-foot runway. They also designed and fabricated
their own lighted distance-to-go markers.
Electrical power hag become a critical element to any beddown
location. with the sophisticated computer and test equipment
required by the Air Force' the demands for reliable electrical
power have increased dramatically since Vietnam. The necessity for
air conditioning in the SEA theater also increased the demands for
electricity. The Air Force used several different sized mission
essential power (MEP)] generators for bare base operations (MEP-4,
40KW; MEP-6; 60KW; MEP-7, 100KW; and MEP-12, 750KW). During the
initial days on site' small portable generators provided electrical
power. The MEP-4,6, and 7 generators were considered as back-up or
emergency generators, yet they were often used to provide primary
power to small clusters of tents or facilities in the early days of
Desert Shield. These required frequent servicing and refueling and
were noisy. This was particularly noticeable because they were
placed near tents (since most personnel were working sixteen to
twenty hour days in the first few weeks, a little generator noise
did not keep them awake). These were replaced by MEP-12A diesel
Document Page: First | Prev | Next | All | Image | This Release | Search