Subject: 92ND ENGR CBT BN HVY UNIT HISTORY
Unit: XVIII CORPS
Parent Organization: ARCENT
Box ID: BX000072
Folder Title: PROBLEM WITH NBC PB PILLS-2 COPIES
Document Number: 1
Folder Seq #: 19
the 92nd for command and control. This brought the battalion
strength to some 900 soldiers and provided great additional
horizontal construction capability. Over the next two months, the
battalion would complete 41 engineer missions, including 244
kilometers of MSR (15 kms of which was asphalted with a single
surface treatment), eight concrete helipads, laying over 2,400
square feet of airfield matting, and 17 other unit life support
projects. These included constructing earthen berms, building
access roads, digging garbage pits, constructing defensive
positions, and building shelters for units' class IX storage needs.
As missions came in, it became apparent horizontal assets were
the critical requirement-. An example was MSR Cadillac, one of the
corps' construction priorities and an important lateral passageway
Northwest for the 24th ID (MECH). The battalion task organized its
earth moving platoons OPCON to Alpha Company and, except for the
single surface treatment work, Cadillac was completed 5 December
1990. Other high priority supply route missions, such as MSR
Volvo, gave the 92nd experience which was to prove useful during
the upcoming Desert Storm phase.
Although not as critical as horizontal missions, vertical
missions kept our carpenters equally busy. Major vertical missions
included : complete renovation of the 24th ID (MECH) battle staff
vans (map boards, tables, light fixtures, and map racks); extensive
rehabilitation of the joint 24th ID (MECH) PMO and Saudi civilian
police relocatable office trailers; placement of five concrete
maintenance pads for the 24th ID (Mech) DISCOM and five concrete
e. Concurrently,
the 92nd provided daily, heavy equipment to neighboring units for
11
Document Page: First | Prev | Next | All | Image | This Release | Search
Document 60 f:/Week-48/BX000072/PROBLEM WITH NBC PB PILLS-2 COPIES/92nd engr cbt bn hvy unit history:01289718521931
Control Fields 17
File Room = sep96_declassified
File Cabinet = Week-48
Box ID = BX000072
Unit = XVIII CORPS
Parent Organization = ARCENT
Folder Title = PROBLEM WITH NBC PB PILLS-2 COPIES
Folder Seq # = 19
Subject = 92ND ENGR CBT BN HVY UNIT HISTORY
Document Seq # = 1
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 28-JAN-1997